Chase Hammock /Tropical Trail / Mocking Bird Lane

Current Statistics as of May. 26, 2017

Project Summary

Project scope: Chase Hammock: this project includes the installation of 8-inch pipe at Chase Hammock Rd. & Judson Rd. (3000 LF)Tropical Trail: this project includes the installation of 6-inch pipe from Church Road to Porcher Road (approximately 2800 LF) and 8-inch pipe from Onsafully Road to near Church Road (approximately 600 LF).

Budget

Current Spent: $89992.86

Budget: $1049992.86

Schedule

Planning: 2014-01-15 00:00 to 2015-01-30 00:00:00

Design: 2015-07-13 00:00 to 2016-10-31 00:00:00

Bid: 2017-05-29 00:00 to 2017-09-25 00:00:00

Construction: 2017-09-26 00:00 to 2018-08-10 00:00:00

Complete: 2018-08-10 00:00 to 2018-08-10 00:00:00