Cocoa Utilities Capital Improvement Program Dashboard

Current Statistics as of Aug. 25, 2017

Overall Progress

 PhaseProjects
 
Planning9
 
Design3
 
Bid1
 
Construction15
 
Complete34
 
Total Projects62

Cost & Schedule Performance

Program is on budget and behind schedule.