Dyal Chemical Conversion & Reliability Improvements

Current Statistics as of Sep. 30, 2020

Project Summary

Project scope: A 54-inch redundant finished water pipeline and vault with a flow meter at the Dyal WTP to provide increased reliability for plant flow,Emergeny Generator Replacement, and Sodium Hypoclorite Upgrade.

Budget

Current Spent: $8,166,908
Budget: $24,806,134

Schedule