Current Statistics as of Jul. 26, 2019

Project Summary

Project scope: A 54-inch redundant finished water pipeline and vault with a flow meter at the Dyal WTP to provide increased reliability for plant flow,Emergeny Generator Replacement, and Sodium Hypoclorite Upgrade.

Budget

Current Spent: $1,033,680
Budget: $2,957,749