Dyal WTP Closed Loop Transition

Current Statistics as of Nov. 30, 2016

Project Summary

Project Complete<

Project scope: Condition assessment of the existing electrical substation and switch gear and upgrading the switch gear to streamline the process of switching to and from backup power in case of an emergency.

Budget

Current Spent: $786142.37

Budget: $786589.08

Schedule

Planning: 2013-10-09 00:00 to 2013-11-21 00:00:00

Design: 2013-11-22 00:00 to 2014-04-17 00:00:00

Bid: 2014-05-05 00:00 to 2014-06-12 00:00:00

Construction: 2014-11-28 00:00 to 2016-10-31 00:00:00

Complete: 2016-10-31 00:00 to 2016-10-31 00:00:00