Filter Covers and Screens at Dyal WTP

Current Statistics as of Nov. 30, 2015

Project Summary

Project Complete

Project Scope: Protection of the groundwater filters from atmospheric conditions and disinfection system improvements to meet FDEP requirements for the 4-log inactivation of viruses.

 

 

Budget

Current Spent: $2251766.69

Budget: $2251766.69

Schedule

Planning: to

Design: 2011-08-31 00:00 to 2012-11-01 00:00:00

Bid: to

Construction: 2012-10-01 00:00 to 2015-09-30 00:00:00

Complete: 2015-09-30 00:00 to 2015-09-30 00:00:00