Groundwater/Surfacewater Clearwell Separation

Current Statistics as of Jun. 30, 2017

Project Summary

Project scope: Separation of the groundwater and surfacewater Clearwell to increase storage capacity and improve operational flexibility and efficiency.

Budget

Current Spent: $7579602.47

Budget: $11392198.92

Schedule

Planning: 2013-10-01 00:00 to 2014-05-27 00:00:00

Design: 2014-06-30 00:00 to 2015-07-31 00:00:00

Bid: 2015-08-31 00:00 to 2015-10-22 00:00:00

Construction: 2016-01-27 00:00 to 2017-11-30 00:00:00

Complete: 2017-11-30 00:00 to 2017-11-30 00:00:00