Industrial Park Pump Station Upgrade

Current Statistics as of Jan. 30, 2019

Project Summary

The project includes the replacement of the 5-Million Gallon (MG) ground storage tank, the replacement of the existing booster pumps, as well as associated building, electrical, yard piping and site improvements.  The project is intended to improve the water system level of service and reliability as a part of the Utility’s ongoing capital improvement program. 

Budget

Current Spent: $5,151,797
Budget: $5,785,840

Schedule