Lift Station #04 Upgrade

Current Statistics as of Sep. 28, 2018

Project Summary

Project Complete

The Lift Station #04 Rehabilitation includes the structural repairs to the wetwell and valve vault and replacement of corroded wet well and valve vault appurtenances.  The valve vault structural repairs includes providing proper drainage to minimize future corrosion.  This reduces collection system failures.

Budget

Current Spent: $680,817
Budget: $736,946

Schedule