Sellers WRF Preliminary Treatment Process (Headworks) Upgrade

Current Statistics as of Sep. 30, 2013

Project Summary

Project CompleteProject Scope: Replacement of the mechanical bar screens, odor control and associated systems at the headworks facility of the Sellers WRF.

Budget

Current Spent: $1034914

Budget: $1034914

Schedule

Planning: 2011-11-28 00:00 to 2011-12-30 00:00:00

Design: 2012-01-02 00:00 to 2012-03-30 00:00:00

Bid: 2012-06-04 00:00 to 2012-08-16 00:00:00

Construction: 2012-08-16 00:00 to 2013-09-30 00:00:00

Complete: 2013-09-30 00:00 to 2013-09-30 00:00:00