Sellers WRF Secondary Clarifier Rehabilitation

Current Statistics as of Sep. 30, 2013

Project Summary

Project CompleteProject Scope: Replacement of the two clarifier mechanisms at the secondary clarifiers of the Sellers WRF, installation of new weir cleaning systems, along with various other rehabilitation activities including protective coatings.

 

 

Budget

Current Spent: $735508

Budget: $783957

Schedule

Planning: to

Design: 2012-01-03 00:00 to 2012-03-30 00:00:00

Bid: 2012-04-01 00:00 to 2012-06-23 00:00:00

Construction: 2012-06-24 00:00 to 2013-06-28 00:00:00

Complete: 2013-06-28 00:00 to 2013-06-28 00:00:00