Surface Water Clearwell and Reject Pond Improvements

Current Statistics as of Jul. 26, 2019

Project Summary

Project scope: Separation of the groundwater and surfacewater Clearwell to increase storage capacity and improve operational flexibility and efficiency.  

Project Complete

Budget

Current Spent: $11,722,956
Budget: $11,780,861

Schedule