• You are here:

Well Field Monitoring System Upgrade

Current Statistics as of Nov. 14, 2014

Project Summary

Project Complete

Project Scope: The project will add or improve pressure and flow instrumentation to allow proper monitoring of flows and pressures for each of the 48 wells in the well field, as well as a comprehensive new communication system in the form of remote radio telemetry from each well site to the Dyal WTP.

Budget

Current Spent: $4,062,627
Budget: $4,062,626

Schedule