Wewahootee Pump Station Upgrade

Current Statistics as of Jun. 24, 2016

Project Summary

Project CompleteProject Scope: Comprehensive upgrade to the Wewahootee WTP Pump Station to increase pumping capacity to 48-mgd, including four new centrifugal pumps,  suction/discharge piping improvements, a new radio communications tower, electrical and HVAC system upgrades and various architectural improvements.

Budget

Current Spent: $4357166.07

Budget: $4429116.38

Schedule

Planning: 2011-09-06 00:00 to 2012-05-25 00:00:00

Design: 2012-08-14 00:00 to 2013-02-21 00:00:00

Bid: 2013-02-22 00:00 to 2013-05-28 00:00:00

Construction: 2013-09-06 00:00 to 2016-05-01 00:00:00

Complete: 2016-05-01 00:00 to 2016-05-01 00:00:00